Author: Robbins

Swift Robbins TBM breaks through 11 Months Early

On May 8 in Nepal’s Sindhuli District a crowd of people attending the breakthrough of a speedy TBM had much to celebrate. The 6.4 m diameter Robbins Double Shield machine had overcome incredibly challenging geology to cross the finish line 11 months ahead of schedule.  Nepal’s Sunkoshi Marin Diversion Multipurpose Project (SMDMP), at 13.3 km in length, is one of the longest TBM-driven tunnels through the Himalayan mountain range and is only the second such tunnel to be completed in the country. View the breakthrough video here.

At a breakthrough ceremony attended by Nepal’s Prime Minister Pushpa Kamal Dahal, the crowd celebrated an epic TBM breakthrough 11 months ahead of schedule.

At a breakthrough ceremony attended by Nepal’s Prime Minister Pushpa Kamal Dahal, the crowd celebrated an epic TBM breakthrough 11 months ahead of schedule.

“The overall design of the Robbins TBM is proven, and the equipment’s performance and integrity are excellent. Additionally, its adaptability to the Himalayan geological conditions is very impressive,” said Mr. Liu Fengfan, SMDMP Project Manager for contractor B-2/COVEC (China Overseas Engineering Group Co. Ltd and China Railway No. 2 Engineering Group Co Ltd).

Ground conditions included two major fault zones with challenging and varied geology ranging from highly jointed mudstone, sandstone and conglomerate to quartzite, granite, and more.  The tunnel was bored through mostly igneous rock with maximum overburden of 1,320 m.

The TBM and its experienced crew were able to persevere through multiple instances of the shield becoming trapped with bypass tunnels required to free it, including one instance 4 km into tunneling that required 27 days’ worth of work to free the machine from collapsing and squeezing ground. Despite the challenges, the crew were able to more than make up the time with swift advance rates including an impressive 1,503.3 m in one month and 72.6 m in one day, both project records set in March 2024.

The success of the machine, despite adversity, is in part due to its proven design. The refurbished TBM was originally used at a smaller diameter on Nepal’s first TBM-driven tunnel, the Bheri Babai Diversion Multipurpose Project (BBDMP). The design incorporates many of the same components of that original machine, and the process involved final assembly on location at the jobsite. It’s something the contractor sees as a positive: “One of the highlights is that this machine integrates the overall structure of the 5.06 m diameter TBM from the Bheri Babai project. After upgrading to 6.4 m diameter, all new front shield components were not assembled in the factory. Instead, we adopted Onsite First Time Assembly (OFTA). This was very effective, and I find it particularly noteworthy,” said Mr. Jin Haikuan, Deputy Project Manager & TBM Production Manager for B-2/COVEC.

With tunneling complete, the work of providing both power and water can begin. The tunnel is connected to a new 28.6 MW surface powerhouse on the Marin River to alleviate the shortage of power supply in the area. It will also be used for farmland irrigation in the districts of Dhanusha, Mahottari, Sarlahi, Rauthat and Bara in the Terai Plain, diverting water from the Sunkoshi River to the Marin River for the project owner, the Department of Water Resources and Irrigation under Nepal’s Ministry of Energy, Water Resources & Irrigation.

The project’s successful completion is a triumph not only for the communities benefiting, but also for the future of tunneling in Nepal. “B-2/COVEC and Robbins have successfully introduced and spread TBM technology in Nepal and shown the advantages of it. This country needs more tunnels,” said Robbins President Lok Home at the breakthrough ceremony. “To have these good performances on these first two projects is really a good thing for the country and our industry.”


NAT 2024

Event Name: North American Tunneling Conference (NAT)
Dates: June 23-26, 2024
Location: Nashville, Tennessee, USA
Venue: Gaylord Opryland Resort & Convention Center
Booth: 901

Come join us in Nashville, TN June 23-26 at the North American Tunneling Conference, the premier tunneling event focusing on current projects, challenges, and successes in tunneling. Stop by our booth 901 to learn more about our ongoing and successful tunneling projects, and be sure to check out our insightful technical presentation.

Technical Presentation

Monday June 24
TBM Technology Session
Presidential Chamber A

11:25 – 11:45 AM

Long Haul TBM: Use of a Rebuilt Main Beam Machine at the DigIndy Tunnel System in Indianapolis, IN
Presented by Doug Harding, Vice President, Robbins & Christian Heinz, Tunneling Division Project Manager, J.F. Shea Construction


World Tunnel Congress 2024

Event Name: ITA-AITES World Tunnel Congress 
Dates: April 19-25, 2024
Location: Shenzhen, China
Venue: Shenzhen World Exhibition & Convention Center
Stand: F04

Come join us April 19-25 in Shenzhen, China for the ITA-AITES World Tunnel Congress, the premiere event for tunneling and underground construction. More than 2,000 professionals are set to take part in the world’s top-attended tunneling conference, where hundreds of technical papers will be presented on the latest topics of interest. Stop by our stand F04 to converse with our expert international team, and find out the latest about our products, projects, and talks at the conference.

Technical Presentation:

Monday April 22
Tech Session 7.1: Guidelines, Reviews & Prospects of Mechanized Tunneling
2:20 – 2:40 PM
CC207, Hall 18
Evaluating TBM Design and Performance, 30 Years Apart: The Lesotho Highlands Water Tunnel, Phase 1 and Phase 2
Presented by Brad Grothen VP Engineering


Use of a Tunnel Boring Machine on Nepal’s First and Second TBM-Driven Tunnels

Nepal’s mountainous terrain has historically been a challenge to tunnel through. That very terrain also holds great promise for hydropower – a resource that the country is now beginning to tap into. Launched in October 2022, a 6.4 m Double Shield TBM is making Nepal’s hydropower plans into a reality as it bores the 13.1 km headrace tunnel for the Sunkoshi Marin Diversion Multipurpose Project (SMDMP). The tunnel is connected to a 28.6 MW surface powerhouse on the Marin River.

The SMDMP is the machine’s second tunnel: on its 12.2km first tunnel (the Bheri Babai Diversion Multipurpose Project/BBDMP), the TBM finished nearly one year early and achieved 1,202 m advance in one month. It was the first instance of TBM use in the country.

In this paper, we examine the successes and lessons learned in Nepal’s mountainous conditions during excavation of both the SMDMP and BBDMP.

 


Robbins Double Shield Sets Record in Nepal

In the southern Himalayan mountains of Nepal, a Robbins Double Shield TBM has crossed into new territory. At the end of June 2023, the machine turned in an impressive advance rate of 1,224.13 m in one month – a record for Himalayan geology and believed to be a TBM record within the Indian Subcontinent. Launched in October 2022, the 6.4 m diameter machine has been boring the 13.3 km headrace tunnel for the Sunkoshi Marin Diversion Multipurpose Project (SMDMP).

The Robbins Double Shield for Sunkoshi Marin

At the end of June 2023, a 6.4 m diameter Robbins Double Shield TBM achieved an impressive advance rate of 1,224.13 m in one month.

Multiple factors played into the successful result. “Proper TBM selection for the existing subsurface is the key reason for success. The Double Shield is the most logical TBM type and has played a major role in this successful journey. Operation, maintenance, and an experienced, dedicated team are additional factors,” said Mitra Baral, Project Director of SMDMP under the Department of Water Resources and Irrigation, part of Nepal’s Ministry of Energy, Water Resources & Irrigation.

Contractor Covec/B-2 echoed those sentiments: “The designed adaptation of the TBM & backup provided by Robbins is verified to be scientific and good under the geology, which are Siwalik stratum and the lower Himalayan zone–both quite complex and variable. The performance of the equipment is generally stable,” said Covec/B-2’s Project Manager, Mr. Liu Feng Fan.

Contractor B-2/COVEC (China Overseas Engineering Group Co. Ltd and China Railway No. 2 Engineering Group Co Ltd) have navigated the Robbins TBM through two major fault zones with challenging and varied conditions ranging from highly jointed mudstone, sandstone and conglomerate to quartzite, granite, and more.

The record result is all the more impressive considering the adversity the machine has overcome to date. Approximately 2,156 m into the excavation the machine became stuck in jointed sedimentary rock, requiring nine days of intensive work and a bypass tunnel to free it. As the machine progressed to more than 4 km in, the geology changed to dolomite, slate, schist, quartzite and phyllite. The machine became stuck a second time 4,669 m in due to collapsing and squeezing ground, requiring a further 27 days of work to release it.

Despite the challenges early on, the machine and its experienced crew have persevered. Currently the TBM is more than 8.3 km into the tunnel and boring in high strength granite, having passed through the two major fault zones predicted on the tunnel alignment. “Timely support from Robbins has made for a good relationship and teamwork. It has been quite important for the success of our project,” said Mr. Liu.

Prajwal Man Shrestha,  General Manager of Robbins Nepal, emphasized that the successful results thus far are a milestone for the use of TBM tunneling in the country: “There are now private sector hydropower developers considering the use of a TBM for their project instead of the conventional D&B method. Very soon we may see that most tunnels longer than 6 or 7 km will be exploring the possibility of using TBMs on their project.”

As for the future of tunneling in Nepal, Mr. Baral is positive it will continue to grow and evolve: “Many TBM projects could be planned for many different areas. Taking into consideration that Nepal is a mountainous country with complex geology, tunnels are indispensable not only for irrigation and hydropower but also roads, railways, water supply, and even metro lines in the cities.”


Final Breakthrough at Bahçe-Nurdaği Railway

In June 2023, a resilient 8.0 m diameter Robbins Single Shield TBM completed its second tunnel at Turkey’s Bahçe-Nurdaği Railway. The machine completed 9.6 km of tunneling, adding on to the 9.2 km it completed in its initial railway tunnel in 2020 – for a total of more than 18 km bored.

Bahce-Nurdag Breakthrough

The Robbins TBM completed 9.6 km of tunneling, adding on to the 9.2 km it completed in its initial railway tunnel in 2020 (pictured) – for a total of more than 18 km bored.

“We are very proud to complete this tunnel in difficult rock formations with our excellent team by utilizing an extremely powerful and strong Robbins Single Shield TBM,” said Deniz Şahin, TBM Chief for contractor İntekar Yapı Turizm Elektrik İnşaat San. ve Tic. Ltd. Şti.

Geology in the second tunnel was comparable to the first, including incredibly hard and abrasive metasandstone with quartz, with an average of 220 MPa (31,900 psi) UCS and a Cerchar abrasion value of 3.87. The rock has some of the most extreme hardness and abrasiveness ever measured in Turkey.

After its first bore in the difficult ground, the machine required some inspection and repairs. “Robbins Field Service was always available when we requested,” said Şahin. “The biggest repairs we undertook with Robbins Field Service technicians were the main bearing seal change and checking and repairing of the TBM before launching it on the twin tunnel after the completion of the first tunnel. Both operations were completed in a short time due to good planning with Robbins technicians.”

The machine began its second bore in February 2021, achieving a best monthly advance rate of 411 m. “During tunneling we performed a normal maintenance program as given in the TBM manual, and the machine had minimum downtime, which shows the durability of Robbins TBM in very hard and abrasive rock,” said Şahin.

Bahce Nurdag TBM launch

The Robbins Single Shield TBM was designed to bore in incredibly hard and abrasive geology including metasandstone with quartz – some of the hardest rock ever encountered by a TBM in Turkey.

“The Robbins TBM has performed extremely well in this project with minimal downtime and good advance rates to complete the longest twin tube railway tunnels in Turkey,” said Yunus Alpagut, Robbins representative in Turkey.

The twin rail tunnels, for owner Turkish State Railways Directorate (TCDD), will provide an economic boost to a region recovering from two consecutively devastating earthquakes with magnitudes of 7.8 and 7.6 that occurred in February 2023. The project site is located very close to the intersection of two large active fault zones, the East Anatolian Fault (EAF) and Dead Sea Fault (DSF).  The tunnels were inspected after the event and were found to have sustained only minor cracking in a few segments. The new rail line will provide service between the towns of Bahçe and Nurdağı, and is part of the TCDD’s plan to overhaul the railway connection in southeastern Turkey by providing a shorter, faster route in one of the country’s busiest railway corridors.


Record-Setting Large Diameter Mixed Ground Tunneling in Turkey: The Eşme-Salihli Railway Tunnel

Large diameter tunneling has historically been seen as a challenge. Add into the equation mixed ground conditions, and it becomes a task that may seem insurmountable. How-ever, a recently completed tunnel in Turkey is a flagbearer for changing the mindset towards these challenging tunneling scenarios that are becoming more frequent. A 13.77 m diameter mixed ground Rock/EPB TBM bored the Eşme-Salihli Railway Tunnel at rates of up to 721.8 m in one month, making it the fastest TBM ever recorded over 13 m in diameter. The machine began its bore in altered gneiss, then passed through mélange consisting of gneiss, sandstone, claystone, mudstone, quartz, and silt. By the end of the bore the machine was excavating in mainly mudstone. Core drillings were taken every 200 m prior to boring.

In this paper, we detail the project as well as analyze factors contributing to the fast advance rates. The factors include TBM choice and system design, ground conditions, TBM utilization rates and downtimes, as well as maintenance practices, crew expertise and technical support, all of which have a part to play in the overall advance rates and successful outcome. Recommendations are made as to best practices in order to achieve good advance rates on similar large diameter, mixed ground tunnels.


Lessons Learned During Excavation of the Incredibly Challenging Yin Han Ji Wei Water Diversion Tunnel

The 2022 breakthrough of an 8 m diameter Main Beam TBM at China’s Yin Han Ji Wei project was a triumph of technology and perseverance – crews at the 17.5 km long tunnel encountered over 14,000 rock bursts, some with energy as high as 4,080 kJ. The rock, consisting of mainly quartzite and granite, was estimated to have a rock hardness of between 107 and 309 MPa UCS, with high abrasivity and a maximum quartz content of 92.6%. The incredibly challenging tunnel also experienced at times severe water inflows, with one particular event exceeding 20,000 m3 of water in one day from a single point. In-tunnel ambient temperatures peaked at 40 degrees Celsius and 90% humidity. Throughout the challenges, the crew and support teams found ways to persevere – whether through unique ground support, or increased monitoring and analysis. In this paper, we will examine the successes and lessons learned in the incredibly challenging ground conditions, determining what worked best to confront each condition as it came up. Recommendations will be made towards what could be used successfully on future projects that en-counter these geological features.


Record-Setting Tunnel Boring Below Lake Ontario at the Ashbridges Bay Outfall Tunnel

The 3.5 km long Ashbridges Bay Outfall in Toronto, Ontario, Canada was a challenging drive set below Lake Ontario. After a remote machine acceptance due to the global pandemic, an 8 m diameter Single Shield machine launched in March 2021 from an 85 m deep shaft and began its bore in shale with limestone, siltstone and sandstone. During excavation, the TBM and its crew bored a city-wide record of 30 rings in one day, or 47 m of advance. This paper will cover the unique project, from TBM acceptance through to launch, tunneling in difficult conditions, and completion in 2022.


Enhanced Probe Drilling & Pre-Grouting on Hard Rock TBMs

While probe drills are not strictly necessary for all projects, the incorporation and use of probe drills and pre-grouting adds capability and insurance to boring operations. Water ingress and unstable ground can be resolved before becoming a problem and resulting in costly delays through the use of enhanced, 360-degree probe drilling setups. To do this, proper design of the array of drill ports in the shield, matched to the possible ground conditions, is critical. For ground with exceptional water and instabilities expected, additional probing locations are low-cost additions that can lower risk and increase efficiency. In this paper we will look at recent and ongoing projects including the Lower Meramec Tunnel and Jefferson Barracks Phase 2. We will detail the design of those probe drill arrangements, and our overall recommendations for probing/grouting systems that best suit challenging ground conditions and keep projects running smoothly.