Author: Robbins

Tunnel Boring below Montreal: A Case Study of Urban Tunneling through Hard Limestone

Montreal, Quebec, Canada’s Rosemont Reservoir tunnel travels for 4.0 km below city streets, faulted rock, a disused quarry, and active subway. The story of the 3.0 m diameter Double Shield TBM’s successful breakthrough involves a careful analysis of geology, TBM operating parameters, and ground consolidation measures. Over the years, geologists conducted two diamond-drilling programs totaling 65 borehole tests to depths ranging from 21 to 65 m below residential and commercial neighborhoods along the tunnel alignment. The core sampling program indicated the presence of medium to thinly bedded limestone, with some shale and intrusive rocks, mainly dykes and sills. While the limestone averaged 50 to 300 MPa UCS, rock in the intrusives ranged from 100 to 430 MPa. More than 80 dykes and sills as small as a few centimeters wide and as large as 8 to 10 m wide were mapped along the 4.0 km tunnel. Contractor Foraction, Inc. took measures including cement injection of vertical boreholes in two suspected fault zones from the surface to a depth of 50 m. Even with these measures, fractured rock and water inflows, which had to be temporarily deviated, slowed progress and required alteration of the boring parameters in some sections. The crew were ultimately successful and made their final breakthrough with the TBM in November 2015. This paper will analyze TBM boring methods and performance based on the changing geological conditions below Montreal. Special attention will be paid to sections in fracture zones and below sensitive structures including the inactive quarry site and active Montreal subway. The authors will analyze how preliminary studies, combined with operational techniques and on-going geological monitoring, resulted in an ultimately very efficient tunnel boring project in a dense urban area.


Hard-working Robbins TBM boring 28 km of tunnels below Indianapolis

On Tuesday, September 6, 2016, one of the longest-running Robbins TBMs embarked on its most extensive project yet.  The 6.2 m (20.2 ft) Main Beam machine, owned by the Shea-Kiewit (S-K) JV, is boring the 8.5 km (5.3 mi) long White River Tunnel as the first in the next phase of the DigIndy wastewater tunnels below Indianapolis, Indiana, USA. In addition to that work, the machine will bore the Lower Pogues Run, Fall Creek, and Pleasant Run Tunnels™ scope of work totaling about 28 km (17 mi) through limestone and dolomite rock.

The rebuilt Robbins hard rock TBM was first used in Indianapolis on the 12.5 km (7.8 mi) long main tunnel, called the Deep Rock Tunnel Connector (DRTC). On that tunnel, the speedy machine achieved world records in its size class of 6 to 7 m (20 to 23 ft), including “Most Feet Mined in One Day” (124.9 m/409.8 ft); “Most Feet Mined in One Week” (515.1 m/1,690 ft); and “Most Feet Mined in One Month” (1,754 m/5,755 ft). “It’s nice to start the job with a machine that has already been proven and successful,” said Stuart Lipofsky, Project Manager for S-K JV.

However the DRTC was far from the TBM’s first job.  The machine, originally built in 1980, has been used on New York City’s Second Avenue Subway, as well as projects in Massachusetts and Canada.  Once the machine has completed the DigIndy network of tunnels, it will have bored more than 51 km (32 mi) of tunnel™n achievement making it one of the hardest working Robbins TBMs ever put into service.  “The age of the machine wasn’t a concern for us, it was a positive. We knew it could perform in harder, abrasive rock,” said Lipofsky.

The machine was launched from the 67 m (220 ft) deep White River shaft following a refurbishment that included new motors, gearboxes, electronics, and other elements. As of the last week of September, the TBM has bored over 300 m (1,000 ft) of the White River Tunnel.  About one mile into the White River Tunnel, the drive will bifurcate eastwards to bore the 2.7 km Lower Pogues Run Tunnel in front of Lucas Oil Stadium in downtown Indianapolis.  The machine will then be backed up to the bifurcation point before continuing north for completion of the White River Tunnel.

As the machine bores, Robbins continuous conveyors remove muck in an extensive system that was highly successful at the DRTC.  Much of the conveyor structure remains the same for the new tunnels, with new horizontal and conveyor belting provided.  The conveyors will wind through curves as sharp as 300 m (1,000 ft) in radius, as the tunnels follow the path of the White River overhead.

The S-K JV has until 2021 to complete the White River and Lower Pogues Run tunnels for local owner Citizens Energy Group, and until 2024 to complete all the tunnels.  The use of one TBM was seen as a positive: “The use of one machine was more efficient for our crews. The schedule allowed us to run with one TBM and we feel we can do it with one machine. It also was a less costly option than running two machines in terms of the owner funding the project,” said Dan Martz, vice president for J.F. Shea.  Once complete, the EPA-mandated deep tunnel project will reduce the amount of raw sewage overflows and clean up tributaries along the White River.


Robbins Small Boring Units: How the Rockhead Works

The Robbins Rockhead is a mid-sized tunneling machine available in both Single Shield and Double Shield models. Ranging between 54 inch (1.35 m) and 78 inch (2.00 m), the Rockhead is the ultimate solution for line-and-grade critical bores that are over 1,000 ft (300 m) in length. Watch this 3D animation to learn more about these powerful machines.


The Robbins Company Announces Joe Lechner to SBU Sales

The Robbins Company announced the appointment of Joe Lechner to the role of Small Boring Unit (SBU) Sales Manager. With over 18 years of industry experience, the role is a natural career progression for Lechner. It brings him back to his early roots of working with SBUs, while more recently he worked with TBMs. Lechner can continue his success with the company in this new capacity with the trenchless division.

In his new position, Lechner will handle SBU sales and rentals for Robbins, assist customers in equipment specifications for projects, and provide full-spectrum customer support. In addition, Lechner will be responsible for many other tasks such as generating quotes for cutters and spare parts, shop scheduling, forecasting, internal operations for Robbins, and field service support, as needed.

“I want customers to know they can come to me with any issues. I have a good understanding of the industry and our business,” said Lechner. “I want to provide an all-around good experience. Robbins wants your project to be successful, with our equipment and support.”

Lechner began working with SBUs in 1998, starting in field service. When he wasn’t out in the field, he was building SBUs and cutters. He started up and commissioned SBU-As in the field, and transitioned over to working with TBMs worldwide in the mid 2000’s. With his diverse worldwide field experience, Lechner’s knowledge will continue to benefit Robbins and its customers.

Lechner said his goals as Sales Manager for the SBU product line for the next two years include increasing stocking levels and providing fast deliveries to customers. He noted the division is streamlining inspection quoting and repair processes to ultimately provide the most efficient services possible. With a few hundred machines in service, some of which are working around the clock, he anticipates product sales, rentals and repairs all will remain consistent moving forward.

“We’re lucky to have Joe working with Robbins,” said Tom Fuerst, Utility Tunneling Sales Manager. “With his background and extensive knowledge, he’ll easily implement the best solutions for our customers.”


Robbins Achieves another Breakthrough in Bangalore

In February 2015, Robbins, with its operating company Robbins India, was asked by Bangalore Metro Rail Corporation Limited to take over the operation and maintenance of two competitor-owned EPBMs. The machines were stalled due to low performance and financial issues from the Operating Contractor and lack of support by the original machine supplier. As the North-South Bangalore Phase 1 Metro tunnels were on the critical path, the BMRC looked to Robbins to step in and take over the troubled project. A Robbins/Robbins India team of 70 field service personnel refurbished and modified the existing equipment, both while in the tunnel and before relaunching the machines in Chickpet station. In addition, the on-site Robbins/Robbins India Team supervised all aspects of TBM excavation, segmental lining, mucking and grout plant operations since the relaunch of the machines for both drives.

“I am particularly proud of being involved in this project, and to support BMRC with the completion of this tunnel drive and bringing the project back on schedule. This is also the first time The Robbins Company has been responsible for the complete scope of operations on a project,” noted Jim Clark, Projects Manager with Robbins India. “One of the biggest challenges we faced was carrying out cutterhead interventions under compressed air in mixed ground conditions that consisted of varying grades of granite in the lower half of the face, and loose, unconsolidated material in the upper section of the face.”

Clark said that on numerous occasions, compressed air would percolate through to the surface, forcing crews to abort cutterhead interventions. They eventually found a solution by pumping a weak mix grout though the mixing chamber, and into the geology surrounding the tunnel face. The weak mix grout stabilized the ground sufficiently so the cutterhead interventions could be completed.

The Robbins crew carried out tunneling operations while the station was being constructed around them to mitigate delays incurred before they took over project operations. The project’s most difficult challenges included a low overburden and consolidated ground along the alignment, and the discovery of several uncharted wells directly on the alignment. In addition, the majority of the tunnel was bored directly beneath buildings constructed upon what is today considered substandard foundations.

This portion of the Phase One Metro tunnels runs from Chickpet to Majestic at Namma Metro. Once Krishna breaks through, the North and South runs of Bengaluru will be connected, allowing service to an average of 40,000 passengers daily. It is being completed under a tripartite agreement between Robbins India, Coastal Projects Limited, the lead contractor, and project owner, Bangalore Metro Rail Corporation Limited. It is anticipated Phase One will be open in its entirety by November, 2016.


A Novel Continuous Conveyor System and its Role in Record-Setting Rates at the Indianapolis Deep Rock Tunnel Connector

The Indianapolis Deep Rock Tunnel Connector (DRTC)—first in a vast network of storm water storage tunnels below Indiana, USA—was a wildly successful endeavor. Crews for the Shea/Kiewit JV drove a 6.2 m Robbins Main Beam TBM to world record rates. The machine achieved 124.9 m/day, 515.1 m/week, and 1,754 m/month in limestone and dolomite rock. The advance rates can be attributed to many factors including ground conditions and knowledgeable crew, but continuous conveyors are also of key importance.

The novel conveyor system, manufactured by The Robbins Company, enabled continuous tunneling in a difficult layout that included two 90-degree curves and two S-curves. Spanning 11,777 m in its longest iteration, the system included nine booster drives plus a main drive. A vertical belt moved muck up the 76 m deep shaft to a radial stacker for temporary storage. The system, one of the most complex in North America and the first to operate in 90-degree curves, made swift tunneling possible.

This paper will examine the world-class tunneling done at the Indianapolis DRTC and the role of continuous conveyance in reaching high advance rates. The logistics of the system will also be examined as it could apply to future tunneling projects with similarly complex layouts.


Use of Two Novel Hybrid-Type “Crossover” TBMs for Hard Rock Conditions with Water Inflows

Mixed ground tunnels come in all kinds. In rock tunnels with possible faults and high pressure water, the challenges are many. With the advent of Crossover TBMs, contractors can minimize risk in such conditions while maximizing efficiency. The newest generation of Crossover is exemplified by two projects in Albania and Turkey.

A 5.56 m Crossover TBM destined for Turkey’s Gerede Water Transmission will be assembled using Onsite First Time Assembly (OFTA) from within an existing tunnel. The unique machine will bore through 30 fault zones requiring the TBM to be sealable to up to 20 bar so pre-consolidation grouting can be done. EPB mode will only be used in poor ground—in this mode, the TBM will bore sequentially using the screw conveyor fore and aft gates.

Skewing further towards hard rock, a unique 6.2 m diameter Double Shield TBM with Crossover features was designed for Albania’s Moglicë Headrace Tunnel. The machine features closure doors and a sealing system to contain inrushes of water until they can be grouted off.

This paper will discuss the unique aspects of the Crossover designs and their utilization at the two projects.


The Next Generation of TBMs for Mining Applications

TBMs have been used in mining in decades past, but their use has been limited and sporadic, due to both perceived and actual application difficulties. With new technology and mounting success stories, this is changing. For both coal and metallurgical mining, deep ore bodies require long access tunnels, and an efficient and economical method of reaching those deposits.

Today, mining engineers are considering TBMs as part of the overall mine development plan. Planned TBM mine drifts are not only longer, but have more complicated trajectories. Mine development TBMs will have to cope with varying geology, potential for high water inflows, steep gradients, and high temperatures. TBM systems are being planned to cope with such difficulties. TBM systems will be considered and increasingly deployed for mine development, even if commodity prices remain low. TBMs can satisfy the need for increased productivity, better life of mine infrastructure, and safety.

This paper will review the historical use of TBMs in mining, and will discuss the 2015 status of TBMs in mining, and the special requirements and adaptable features needed in order to make efficient TBMs a reality in mines worldwide.


Concurrent Segment Lining and TBM Design: A Coordinated Approach for Tunneling Success

The success of a tunnel project relies on many factors, but one of the most important is also the most overlooked: coordination by all parties involved during the design stages. This is particularly true of segment design and TBM design. Tunnel lining with segmental rings is usually designed according to the standards of reinforced concrete construction based on a given GBR. However, for TBM tunneling, the determination of loads during ring erection, advance of the TBM, earth pressure, and bedding of the articulated ring are all part of the tunnel lining design as well. TBM design can be heavily affected by the segment arrangement, dimension, and weight, but these are usually given as a fixed input to the TBM manufacturer—a process that can cause unnecessary complications.

The authors propose that the industry evaluate the process as it stands. In order to find the optimum balance between lining design and TBM cost and operational workflow, both designs should be finalized concurrently. This requires coordination between the TBM manufacturer and segment designer from the early stages. The aim of this paper is to evaluate the influence of the segment lining design on TBM cost and performance, and to provide commentary on existing design guidelines to optimize lining and TBM procurement.


Mexico's Crossover TBM makes its Mark for Robbins

On March 29, 2016, North America’s first Crossover TBM broke new ground in Mexico City.  The 8.7 m (28.5 ft) diameter Robbins XRE™ –a cross between a rock TBM and an EPB–emerged into an intermediate shaft at Emisor Poniente (TEP) II.

The machine is undergoing some maintenance before continuing on to bore the final 3.2 km (2.0 mi) of tunnel.  The customized TBM, for a consortium of Aldesem, Proacon, and Recsa, was chosen based on a number of parameters that included challenging ground conditions below an area to the west of downtown Mexico City.

The tunnel path travels through a mountain with cover as high as 170 m (560 ft), through fault zones and in a section with cover as low as 8.0 m (26.2 ft) above the tunnel crown.  Much of the tunnel consists of andesite rock with bands of tuff, and softer material in fault zones as well as an 874 m (2,870 ft) long section in soft ground at the end of the tunnel.

“The geological profile of the project comprises six different lithologies, among them hard rock such as dacite.  To get the best operation in both areas required use of dual mode technology such as the Crossover TBM,” said Enrique del Castillo of contractor Aldesem. The 8.7 m (28.5 ft) diameter Robbins XRE (Cross between Rock/EPB) is a design that allows for the TBM to effectively bore in both hard rock and mixed ground.

The machine setup includes a canopy drill and positioner for enhanced ground consolidation, as well as gear reducers to adjust torque and RPM based on ground conditions. The TBM, initially launched in hard rock mode, can be operated in EPB mode later on by switching out the belt conveyor with a screw and converting the cutterhead.

The Robbins Crossover machine began its journey in August 2015, and advance rates picked up quickly. Project records were set in January 2016 after the machine achieved a best day of 42.8 m (140 ft) and a best week of 185.1 m (607 ft). By mid-March the machine had bored through the first of the contact zones, a 30 m wide section of fractured and blocky rock. While the excavation through the contact zone was slow going, progress picked up again in the more competent rock. Final breakthrough is expected in autumn 2016.

Once complete, the 5.8 km (3.6 mi) tunnel will supplement an existing and overtaxed wastewater line built in the 1970s. The deep drainage tunnel will serve to prevent recurrent flooding in Valle Dorado, and will benefit the cities of Cuautital Izcalli, Tlalnepantla, and Atizapan de Zaragoza, an area with a total population of 2.1 million inhabitants.